Our Projects

The buildings that can’t afford to get it wrong

Five years on some of the UK’s most demanding projects, including The Gherkin, Olympic Park and Grosvenor Square, with 54 companies served. Each one was delivered to the same rule: evidenced before cover-up.

I cannot recommend them highly enough!

“A final report was provided that gave the management team the confidence that the work had been carried out and the evidence to show that we had corrected the identified issues.”

David Mills Building management · 43-unit residential building
Landmark London projects

Trusted to work on the UK’s highest-profile buildings

The register below lists the projects. Each entry carries the same evidence discipline: photographed as installed, captured in the golden thread, and handed over audit-ready.

The Gherkin30 St Mary Axe, London Commercial Beam-clad system & firestopped cavities
Challenge

Several floors of The Gherkin were stripped back to the building's structure and rebuilt as open-plan office space for a new tenant. The strip-out exposed structural steelwork and opened voids around the perimeter of every floor. Both needed tested fire-protection solutions.

Solution

Skyline was brought in early. Working closely with the principal fire engineer, we identified appropriate tested systems, installed a Rockwool beam-cladding system to protect the exposed steelwork, closed the perimeter floor voids and fitted fire curtains where required.

Outcome

It was a fast-moving project. Technical challenges surfaced as the works progressed, and we resolved them without holding up the programme. The package came in on time and within budget, and the relationship built with the principal contractor has carried through to subsequent projects.

Olympic ParkLondon Mixed-use Firestopping package, office-to-residential conversion
Challenge

Olympic Park was one of the largest projects a long-standing Skyline client had undertaken at the time. We were appointed to deliver the firestopping package across the development.

Solution

Earlier delays to the groundworks had squeezed the construction programme, so the later trades worked to a significantly accelerated timetable. Our systems and site team kept installation moving at pace. Coordination mattered most: service penetrations had to be made available and firestopped at the right stage, without clashes or delays between trades.

Outcome

This project proved that effective compartmentation is a collaborative effort across the whole construction team, not the firestopping contractor working alone. We still work at the development today. As new services and technologies enter the building, we maintain and alter the firestopping to match.

Grosvenor Square HouseMayfair, London Residential Compartmentation & firestopping, former Canadian Embassy, 48 apartments
Challenge

Grosvenor Square House was a different kind of project for Skyline: the conversion and refurbishment of an existing building into a high-end residential property. Work at this level demands more than a high standard of installation. It calls for professionalism, attention to detail and the ability to work alongside a wider team delivering a premium finish.

Solution

The age and existing construction of the building meant standard firestopping details were not always available. Skyline worked with the design team, architects, principal contractor and manufacturers to identify tested details and solutions for these areas.

Outcome

The works were delivered on programme and within budget. Skyline had already completed several smaller projects for this client. After Grosvenor Square House, we became their preferred firestopping contractor.

Aviator ParkAddlestone Commercial Firestopping & cavity barriers
Challenge

Aviator Park was one of a series of commercial-to-residential conversions delivered for a repeat Skyline client. Beyond the general firestopping and compartmentation package, the existing construction threw up some technically challenging interfaces, particularly where glazing, structural steelwork and different construction details met.

Solution

Skyline worked with the client and the relevant manufacturers to establish suitable solutions for these more complicated areas, and delivered the works on programme and within budget.

Outcome

The biggest benefit came later. By the time we moved onto the subsequent buildings in the programme, we had already dealt with most of these interfaces, so potential issues were raised with the project team before they became problems on site. Early engagement let details and sequencing be agreed in advance, reducing remedial works, delays and extra cost.

Royal HeightsReading Residential High-rise compartmentation
Challenge

Royal Heights shows what happens when Skyline joins a project that is not going to plan. We tendered for the works originally but were not appointed. Part-way through the job, difficulties arose with the firestopping package, and the contractor parted ways with the original specialist.

Solution

Skyline was approached to take over the remaining works. The handover point was relatively clean, and the project was early enough for us to take responsibility for most of the remaining package. We mobilised quickly, agreed expectations with the wider project team and picked up where the previous contractor left off.

Outcome

From there, the remaining firestopping was delivered without further disruption or unexpected commercial issues. The project completed successfully. It led to further work for the client, and Skyline ultimately became their preferred firestopping contractor.

Voyager HouseFeltham Residential Compartmentation survey & works, 52 apartments
Dolphin HouseLondon Residential Firestopping remedials, six-storey apartment building
Clive HouseWeybridge, KT13 Commercial Externals & communal areas
Elmhurst Primary SchoolLondon E7 Education Custom fire safety package
Coombe Hill HouseOffice-to-residential conversion Residential Cavity barriers & sealing, 128 residential units
DC Douglas CourtBerkshire Residential Former care home conversion
BC Brechin CourtBerkshire Residential Four-storey apartment block
KH Kingmaker HouseLondon Residential 137 apartments
They were always available to answer any questions and were proactive in keeping me informed throughout the project.
Phillip Smith Commercial firestopping project
From the founder
The best fire stopping job I’ve ever done or been involved in was probably Windsor Castle.
Tom Ford Founder, Skyline Firestopping · Making our cities safer

Tom fronts Skyline. In this short clip he tells the story of a door upgrade at Windsor Castle, in his own words: the building, the history, and why he rates it the best job he has been part of.

Read the video transcript

The best fire stopping job I've ever done or been involved in was probably Windsor Castle. And obviously Windsor Castle famously burned down in, I think it was the 90s, there was a massive fire and they had a huge issue there. I did a job there where we upgraded some doors, really old doors in Windsor Castle. And I just got a real kick out of being at Windsor Castle and working there and having my business there and working for the Queen. And she was alright, you know, she paid her bill on time.

BM TRADA Q-Mark — Fire Stopping Installation certification
Independent certification

Third-party certified

BM TRADA Q-Mark certification: tested systems installed exactly as tested, verified independently rather than on our word.

  • Highly experienced, certified team (NVQ Level 2, full SKEB competence matrix)
  • Progressing our ASFP membership application
  • Progressing our SafeContractor registration
Their attention to detail, commitment to quality, and customer-focused approach set them apart from other service providers.
Sally Christmas Residential firestopping project
Talk to a specialist

Looking for advice on your project?

Talk through your building and your programme with the team behind these projects.